Realigning Budgets and Achieving Cost Savings with Eolus

Overview

In January 2024, a Fortune 100 company faced budgetary challenges for a complex office fit-out project comprising three unique program elements.

Initially constrained by an internal budget of $7 million-far below the estimated $11.6 million construction cost-the company leveraged Eolus to realign their budget and reduce costs.

Through collaboration and program refinement, the final Guaranteed Maximum Price (GMP) was negotiated down to $9.2 million, ensuring the project's success.

Adjusting in Real-Time

The customer approached Eolus with a mission-critical office fit-out project that included pre-in- stalled flooring, an articulating stairway, and exposed brick finishes.

The customer's $7 million internal budget quickly proved insufficient due to complexities in design and escalated material costs. They sought a solution to balance their financial constraints with the project's unique design requirements.

Budget Discrepancy

The customer faced a $4.6 million discrepancy between their internal budget and the initial cost estimate of $11.6 million.

The miscalculation stemmed from misapplication of rentable square footage (RSF) metrics to net square footage (NSF) and a failure to account for material cost escalations from 2021-2022.

Eolus was tasked with delivering an optimized budget aligned with the customer's goals and constraints.

Customized Solution

Eolus developed a customized budgetary estimate, leveraging historical project data and programmatic analysis to create a baseline.

The team worked collaboratively with the customer's internal teams, architects, and construction managers to realign scope and achieve a feasible budget.

Key cost-saving strategies included adjusting programmatic allocations; reducing the scope of ceiling designs, control systems, and acoustic ratings; and deferring non-essential features such as lobby spaces.

Eolus in Action

  1. Initial Estimate Development

    Eolus provided a preliminary budget of $11.6 million based on programmatic information. The customer revealed their internal $7 million budget, prompting immediate recalibration.
  2. Collaborative Renement

    Eolus initiated transparency-driven discussions to align scope with financial constraints. Adjustments reduced the budget to $9.6 million, with detailed alternatives presented to the customer.

  3. Architectural and GC Engagement:

    Revised estimates informed the Schematic Design (SD) phase. The design package was sent to a general contractor, resulting in a GMP estimate of $9.9 million

  4. Negotiations

    The customer used Eolus's detailed cost break- down to negotiate the GMP down to $9.2 million.

Measurable Results

By integrating Eolus, the customer achieved:

Cost Savings

A final GMP of $9.2 million, saving over $2.4 million from the initial estimate.

Enhanced Decision-Making

A final GMP of $9.2 million, saving over $2.4 million from the initial estimate.

Improved Eficiency

Streamlined communication and real-time budget insights minimized delays and cost overruns.

Eolus proved essential in aligning the project's financial and design goals, ensuring seamless execution from start to finish.