Realigning Budgets and Achieving Cost Savings with Eolus
Overview
In January 2024, a Fortune 100 company faced budgetary challenges for a complex office fit-out project comprising three unique program elements.
Initially constrained by an internal budget of $7 million-far below the estimated $11.6 million construction cost-the company leveraged Eolus to realign their budget and reduce costs.
Through collaboration and program refinement, the final Guaranteed Maximum Price (GMP) was negotiated down to $9.2 million, ensuring the project's success.
Adjusting in Real-Time
The customer approached Eolus with a mission-critical office fit-out project that included pre-in- stalled flooring, an articulating stairway, and exposed brick finishes.
The customer's $7 million internal budget quickly proved insufficient due to complexities in design and escalated material costs. They sought a solution to balance their financial constraints with the project's unique design requirements.
Budget Discrepancy
The customer faced a $4.6 million discrepancy between their internal budget and the initial cost estimate of $11.6 million.
The miscalculation stemmed from misapplication of rentable square footage (RSF) metrics to net square footage (NSF) and a failure to account for material cost escalations from 2021-2022.
Eolus was tasked with delivering an optimized budget aligned with the customer's goals and constraints.

Customized Solution
Eolus developed a customized budgetary estimate, leveraging historical project data and programmatic analysis to create a baseline.
The team worked collaboratively with the customer's internal teams, architects, and construction managers to realign scope and achieve a feasible budget.
Key cost-saving strategies included adjusting programmatic allocations; reducing the scope of ceiling designs, control systems, and acoustic ratings; and deferring non-essential features such as lobby spaces.
Eolus in Action
- Initial Estimate Development
Eolus provided a preliminary budget of $11.6 million based on programmatic information. The customer revealed their internal $7 million budget, prompting immediate recalibration.
- Collaborative Renement
Eolus initiated transparency-driven discussions to align scope with financial constraints. Adjustments reduced the budget to $9.6 million, with detailed alternatives presented to the customer.
- Architectural and GC Engagement:
Revised estimates informed the Schematic Design (SD) phase. The design package was sent to a general contractor, resulting in a GMP estimate of $9.9 million
- Negotiations
The customer used Eolus's detailed cost break- down to negotiate the GMP down to $9.2 million.

Measurable Results
By integrating Eolus, the customer achieved:
Cost Savings
A final GMP of $9.2 million, saving over $2.4 million from the initial estimate.
Enhanced Decision-Making
A final GMP of $9.2 million, saving over $2.4 million from the initial estimate.
Improved Eficiency
Streamlined communication and real-time budget insights minimized delays and cost overruns.
Eolus proved essential in aligning the project's financial and design goals, ensuring seamless execution from start to finish.